Implementation of the Largest Digital Substation in the U.S. Metals Industry: A Big River Steel Case Study


Big River Steel has deployed a large-scale digital substation at its new 3-million-ton capacity facility in Osceola, Ark., USA. The digital substation applied IEC 61850 standards, intelligent electronic devices, switching infrastructure and SCADA integration to enhance reliability and operational safety in steelmaking. This paper shares the conceptualization, technical solutions, decision-making, testing and operational benefits of the implementation. A discussion on lessons learned, and the impact on schedule and execution models, provide guidance for future digital substation projects in the metals industry and other energy-intensive sectors.

Authors:

Mr. Timothy Burttram | Big River Steel - A U. S. Steel Co.
 

Mr. Jason Cudd | Big River Steel - A U. S. Steel Co.
 

Mr. Ramesh Khajjayam | Primetals Technologies USA LLC
 

Mr. Anil Kanagala | Primetals Technologies USA LLC
 

Mr. Kyle Hambright | CVE Technologies Group
 

Mr. John Wellington Da Silva Brandao | Siemens Industry Inc.
 

Session Chairs:

Cecil Wristen |
 

Implementation of the Largest Digital Substation in the U.S. Metals Industry: A Big River Steel Case Study

Category

Presentation Only

Description

Custom CSS

double-click to edit, do not edit in source


Session: Electrical Applications: Power Systems
Track: Electrical Applications
Date:
5/5/2026
Session Time: 2:00 PM to 5:00 PM
Presentation Time: 02:30 PM to 03:00 PM


Back to Session

  • Powered by OpenWater: Application and Review Software